Construction Updates

Water and Sewer Improvements will start on Monday, April 7th. 

Work will begin on 7th Street at Bismarck Avenue and head north past Bookwalter Avenue.  All work this year will be open trench.

It is estimated that it will take Tand Construction about 8 weeks (weather pending) to complete the remaining water and sewer improvements.

Paving will take an estimated additional 3 weeks (weather pending) to complete once the water and sewer improvements are completed.